| Wk 1 | Aug 18 | - Unit 1: Introduction to Virtualization
- Class organization and groups
- Overview of Springfield VMware vSphere Environment
- Deploy a virtual machine
- Install and update Rocky Linux
- Confirm Setup and Connectivity of VMs
| - Groups and Tools
- Group Assignments
- VCAT
- Week 1
- Supplemental Resources:
- Hands-On Microsoft Windows Server 2019: p. 155-167
| |
| Wk 2 | Aug 25 | - Introduction to VM Templates
- Linux Apache Server
- Configure Client VM with GUI
| - Week 2
- Create a VM Template
- Create and Deploy From Templates
- Supplemental Resources:
- Hands-On Microsoft Windows Server 2019: p. 185-190
| Due Mon (8/24): Lab Activity 1A & 1B |
| Wk 3 | Sept 1 | - Create a LAMP web application system
- LAMP - Linux/Apache/MySQL/PHP
| - Week 3
- Config the Webmin Repository
- Config MariaDB
- Install PHP and Wordpress
| Due Mon (8/31): Lab Activity 2A & 2B |
| Wk 4 | Sept 8 | - Unit 2: Windows Server
- Installing Windows Server 2025
- Domain Name System (DNS) Configuration
- Work on Lab Project 1
| - Lab Projects
- Week 4
- Supplemental Resources:
- Hands-On Microsoft Windows Server 2019: p. 506-528
| Due Mon (9/7): Lab Activity 3 |
| Wk 5 | Sept 15 | - Hardware in an Enterprise Data Center
- Configure and Manage Data Storage
- RAID Configurations
| | Due Mon (9/14): Lab Project 1 and Lab Activity 4 |
| Wk 6 | Sept 22 | - IP Addressing and Subnetting
- GROUP DNS Server Assignment and Cleanup
| | Due Mon (9/21): Lab Activity 5 |
| Wk 7 | Sept 29 | - Configure New DHCP Server Profile
- Install DHCP on group DNS Server
- Deploy New VM from Template
| - Week 7
- Supplemental Resources:
- Hands-On Microsoft Windows Server 2019: p. 542-561
| Due Mon (9/28): Lab Activity 6 |
| Wk 8 | Oct 6 | | - Review Midterm Exam Study Guide on Canvas
| Due Mon (10/5): Lab Activity 7 |
| October 12 - 18: Fall Break - No Class |
| Wk 9 | Oct 20 | - Active Directory
- Deploy and Config a Domain Controller
- Organizational Unit Structures
| | |